Construction update for the week of November 28, 2016

The following construction activities are scheduled for the week of November 28, 2016 – Academic Core Buildings:

Building 1 (Science): Remaining Footing Rebar will be installed this week. Work will continue with the footing/pit starts and remaining concrete will be poured on December 2. Rat slab will be poured this week. Site Utilities – Firewater/Electrical & Pool Piping installation continues in the south side wall. Excavation of site/wall footings in progress.

Building 2 (Arts):  Staking of Drilled Piers will be completed this week. Work continues with the under slab Sub drains and MEPs.

Building 3 (Learning Commons): Work will continue with the underground utilities. Under slab MEPs Plumbing continue along with Footing Pits and Rebar. Footings and pits in progress. Rat slab will be poured this week, along with footing rebar.

North Site Utilities: Excavate and install sanitary sewers. Inspections continue with the Union Sanitary District. Excavate and install storm drains.

As the pier drilling work continues from Building 3 to Building 2 it will be closer to the Smith Center with a potential for noise impacts. No other heavy construction operations are anticipated during this period.

Posted in Uncategorized

Construction Updates for the week of November 21, 2016

Academic Core Buildings:

  • Building 1 (Science): Work will continue with the footing/pit starts. Concrete pour has been rescheduled to 11/22 & 23. Footing Rebar will continue this week. Site Utilities – Firewater/Electrical & Pool Piping installation continues in the south side wall.
  • Building 2 (Arts):  Work continues with the Staking of Drilled Piers . Rebar cages continue to be delivered to the site with Drilled Piers following Building 3. Under slab Sub drains and MEPs are in progress.
  • Building 3 (Learning Commons): Work will continue with the underground utilities. Under slab MEPs Plumbing are in progress along with Footing Pits and Rebar.
  • North Side Utilities: Excavation and inspection of Storm Sewer by Union Sanitary District. Excavate and install Storm Drains. 

As the pier drilling work continues to progress from Building 3 to Building 2 it will be closer to the Smith Center with a potential for noise impacts. No other heavy construction operations are anticipated during this period.

Posted in Uncategorized

Construction Update for the week of November 14, 2016

Academic Core Buildings

  • Building 1 (Science): Work will continue with the footing/pit starts and concrete will be poured on November 17. Footing Rebar will be installed this week. Site Utilities – Firewater/Electrical & Pool Piping installation continues in the south side wall.
  • Building 2 (Arts):  Work continues with the Staking of Drilled Piers . Rebar cages are being delivered to the site with Drilled Piers following Building 3. Under slab Sub drains and MEPs are in progress.
  • Building 3 (Learning Commons): Work will continue with the underground utilities. Under slab MEPs Plumbing are in progress along with Footing Pits and Rebar.

As the pier drilling work progresses from Building 3 to Building 2 it will be closer to the Smith Center with a potential for noise impacts. No other heavy construction operations are anticipated during this period.

Posted in Uncategorized

Construction Updates for the Week of November 7

The following construction activities are scheduled for the week of November 7, 2016 – Academic Core Buildings:

Building 1 (Science): Work will continue with foundation footings and setting of the tie down plates. Footing Rebar will be delivered on site. Storm Drain installation continues in the south side wall.

Building 2 (Arts):  Foundation pads will be certified and drilled piers will be staked. Rebar cages will be delivered on site and drilled pier installation will follow building 3.

Building 3 (Learning Commons): Overbuild at foundation pads will be removed and work will continue with the underground utilities.

Posted in Uncategorized

Construction Updates for the week of October 31

·         Building 1 (Science): Installation of foundation footing anchor bolts; Installation of Foundation Footing Rebar; Installation of site Storm Drains; Stake out south site wall footings (adjacent to building 9)

·         Building 2 (Arts): Final preparation of building pads; Stake out all drilled piers; Rebar cage deliveries; installed drilled piers;

·         Building 3 (Learning Commons): Preparation of the underground utilities, mechanical / electrical / plumbing.

 

Posted in Uncategorized

CONSTRUCTION IMPACT NOTICE

 Core Drilling Scheduled in Lots D & E:

As part of an initial investigation and required by the Alameda County Water District a test bore for the proposed Geothermal project is scheduled to be conducted on September 12th and 13th , 2016 in Parking Lot E are part of Lot D.
This area is located in the area north of the new Soccer Field.  A construction fence will be placed in this area that will impact approximately 30 stalls in these lots. Please use caution when driving and walking in this areas as it is an active construction zone.
We apologize for any inconvenience that this may cause. Thank you.

 

Posted in Uncategorized

CONSTRUCTION IMPACT NOTICE:

Due to ongoing construction between the new Soccer and Softball Fields, we will have to temporarily close off Olive Way from the western edge of the new fields to just before Building 20. This closure is expected to occur between Monday, August 8th through Thursday, August 12th.  Signs will be posted at key locations indicating alternate pedestrian access in and around this area. We apologize in advance of inconveniences that it might incur.

Thank you for your patience and understanding.

 

Posted in Uncategorized