Construction Update for the week of December 19, 2016

UPDATE: Construction Taking Place Starting Monday, December 19, 2016

Ohlone College continues to make progress with our construction projects at the Fremont campus. Some of these projects occasionally require temporary closures and changes to our campus areas. While every effort is made to minimize these impacts, some are unavoidable.  As a result, we would like to inform everyone of some upcoming projects and what their effects will be on parking and transportation.

Pine Street/ Key D Road Work:

Project Timeline: December 19, 2016 – January 20, 2017 (projected completion)

IMPACT:

  • Pine Street will be closed from the tennis court access road up to Key D
  • AC Transit bus stop in Key D will be temporarily closed
  • A temporary bus stop for the 210 & 217 buses will be located in the Promenade Circle near the 5th level of the South Parking Structure and Building 7 during construction
  • Key C bus stop for the 210 & 217 buses will continue to be operational

Key B and Parking Lot A Closed for Geo-Thermal Project:

Project Timeline: December 19, 2016 – Mid March 2017

IMPACT:

  • Key B and parking lot A will be closed at Witherly Lane
  • Staff parking, ADA parking, and electric vehicle charging stations will be inaccessible in parking lot A during this time
  • Pedestrian pathway will be accessible to and from the swing space (portables) and upper campus
  • Alternate staff parking locations will be available in lots: U, V, W, D, and the South Parking Structure
  • Alternate ADA parking will be available in lots: K, R, T, U, P, and the South Parking Structure

Please contact Campus Police Services at 510-659-6111 if additional assistance is needed

  • Alternate electric vehicle charging stations are located in parking lots H near building 19 or the 2nd level of the South Parking Structure

Parking Lots E & H and Olive Lane Drive Through – Pavement Work and Striping:

Project Timeline: December 21, 2016 – January 22, 2017

IMPACT:

  • Partial closure of Parking Lots E & H to conduct pavement and stripping work to establish walkways, add additional parking stalls, and change vehicle direction flow for increased traffic safety

Pedestrian Walkway at west side of swimming pool and building 9:

Project Timeline: December 27, 2016 – January 20, 2017

               IMPACT:

  • Pedestrian pathway will be completely blocked off for reconstruction beginning near the South Parking Structure to the west side of building 9
  • Access from the South Parking Structure to building 9 and the swimming pool will be available will be available on the east side of the SPS on the second level
  • From the South Parking Structure, utilize Key C sidewalk to walk to Hyman Hall, upper and lower swing space (portables), and building 20

Thank you for your patience during the construction process.

For questions or concerns regarding parking and accessibility please contact Campus Police Services at 510-659-6111.

Posted in Bus Stops, Parking / Parking Lots

Construction updates for the week of December 12, 2016

Academic Core Buildings:

Building 1 (Science): Remaining Footing Rebar will continue to be installed this week. Formwork to foundation footings have been stripped. Rat slabs will be poured this week. Pool pipe and Ground Loop is scheduled for this week.

Building 2 (Arts):  Work continues with the under slab Sub drains and MEPs. Footing excavations to start this week.

Building 3 (Learning Commons): Footings and pits in progress. Footing rebar installation will continue this week.

North Site Utilities:  No work has been scheduled this week.

All pier drilling for the foundations have been completed. No other heavy construction operations are anticipated during this period. There will be minimal construction activities during the Holiday break.

Posted in Building 1 SCIENCE, Building 2, Building 2 ARTS, Building 3 LEARNING COMMONS

Construction Updates for December 2016 to March 2017

Pine Street/ Key D Road Work:

Project Timeline: December 19– January 2 (projected completion)
IMPACT:

  • Pine Street will be closed from the tennis court access road up to Key D
  • AC Transit bus stop in Key D will be temporarily closed
  • A temporary bus stop for the 210 & 217 buses will be located in the Promenade Circle near the 5th level of the South Parking Structure and Building 7 during construction
  • Key C bus stop for the 210 & 217 buses will continue to be operational

Key B and Parking Lot A Closed for Geo-Thermal Project:

Project Timeline: December 19 – Mid March
IMPACT:

  • Key B and parking lot A will be closed at Witherly Lane
  • Staff parking, ADA parking, and electric vehicle charging stations will be inaccessible in parking lot A during this time
  • Pedestrian pathway will be accessible to and from the swing space (portables) and upper campus

Parking Lots E & H and Olive Lane Drive Through – Pavement Work and Striping:

Project Timeline: December 21 – January 22
IMPACT:

  • Partial closure of Parking Lots E & H to conduct pavement and stripping work to establish walkways, add additional parking stalls, and change vehicle direction flow to increase traffic safety

Thank you for your patience during the construction process.

For questions or concerns regarding parking and accessibility please contact Campus Police at 510-659-6111.

Any changes that may occur to this schedule will be posted accordingly.

Posted in Uncategorized