Construction Update for the week of June 13, 2018 & Summer Information

construction activities that are planned for this month and over the summer: Construction fences have been be put up around the Main Street site and began with the Abatement Contract for Building 3. This work is scheduled to started on June 11

Posted in Academic Core Buildings, Building 4, Building 5, Building 6

Friday, May 29: Fremont Campus Buildings 2, 3 & 4 Water Shutdown

A water shutdown for Buildings 2, 3 and 4 on the Fremont Campus is scheduled for Friday, May 29.  An all-day shutdown is anticipated.

Posted in Building 2, Building 4