Construction updates for the week of December 12, 2016

Academic Core Buildings: Building 1 (Science): Remaining Footing Rebar will continue to be installed this week. Formwork to foundation footings have been stripped. Rat slabs will be poured this week. Pool pipe and Ground Loop is scheduled for this week.

Posted in Building 1 SCIENCE, Building 2, Building 2 ARTS, Building 3 LEARNING COMMONS

Friday, May 29: Fremont Campus Buildings 2, 3 & 4 Water Shutdown

A water shutdown for Buildings 2, 3 and 4 on the Fremont Campus is scheduled for Friday, May 29.  An all-day shutdown is anticipated.

Posted in Building 2, Building 4

January 15, 2015 Update

The Academic Core construction site was secured.  Buildings 1, 2 and 8 are now inaccessible to all non-authorized personnel. The mail room was moved to FP 29.  However, it will not be ready for “prime time” use until Tuesday morning,

Posted in Building 1, Building 2, Building 8, Fremont Campus, Fremont Portables (FP)