Blog Archives

Construction Update for the week of May 11, 2018

  Emergency Access from Building 9 – 2018 Graduation:   As was required last year, Emergency Egress as required by the Fremont Fire Department is being installed from exit doors of the north side of the Gym in Building 9.

Posted in Uncategorized

Construction Update for the month of APRIL 2018

DEMOLITION OF EXISTING BUILDING 3: Building 3 is scheduled to be demolished starting on May 20, 2018. This work is part of the Academic Core project that will be converted into an outdoor landscape area at the North East end

Posted in Uncategorized

Construction update for the month of November 2017

Progress continues to be made with the Academic Core project. Backfill around the buildings is in progress.  Exterior Scaffolding has been installed in Building 1 and continues with Buildings 2 and 3. Plans are underway to Shrink Wrap the buildings

Posted in Uncategorized