Construction Updates for the Month of February 2018

 

    • Progress continues to be made with the Academic Core project. Work is progressing well with all 3 buildings to include interior wall framing, Mechanical, Electrical & Plumbing preparations and fire proofing.
    • Drywall is being installed in selected areas of all three buildings. Scaffolding is being installed in building 2 in preparation for the final phase of Shrink Wrapping. Buildings 1 and 3 are now 95% Shrink wrapped and building 2 is 75%. The plan is to have all buildings Shrink Wrapped by mid-March. Work is progressing with the large lecture hall in building 1 with framing and installation of the roof.
    • The Design Development plans have been completed for the North Parking project. Work will now continue into the Construction Document phase.
    • Building 5 Renovation: The Architects are now proceeding into the Construction Document phase. A Preliminary Cost Estimate for the project has been developed for review and approval by the college.
    • Newark Security Upgrade: Plans for the project are at the 90% construction document phase.  Bid documents are now being prepared for possible bid opening in March.
Advertisements
Posted in Academic Core Buildings, Building 5, Newark Campus, Parking Lots

Construction Update for the Month of January 2018

Progress continues to be made with the Academic Core project. Work is progressing well with all 3 buildings to include interior wall framing, Mechanical, Electrical & Plumbing preparations and fire proofing. Drywall installation is in progress in parts of building 1 and 3.  Exterior Scaffolding has now been completed installed in Building 1 and 3.

The Design Development plans have been completed for the North Parking project. Work will now continue into the Construction Document phase.

Building 5 Renovation: The Architects are now proceeding into the Construction Document phase. A Preliminary Cost Estimate for the project has been developed for review and approval by the college.

Hyman Hall Renovation: A final program document has been submitted to the college for its review and approval.  After the approval of the final program and budget, the Architects will continue with the next stage of the design phase.

Newark Security Upgrade: Plans for the project are at the 80% construction document phase.

 

Posted in Academic Core Buildings, Building 5, Hyman Hall, Parking / Parking Lots

Construction update for the month of November 2017

Progress continues to be made with the Academic Core project. Backfill around the buildings is in progress.  Exterior Scaffolding has been installed in Building 1 and continues with Buildings 2 and 3. Plans are underway to Shrink Wrap the buildings to prepare for the upcoming Winter season.

The Design Development plans have been completed for the North Parking project. Work will now continue into the Design Development phase.

Building 5 Renovation: The Architects are now proceeding into the Schematic Design phase. A meeting has been scheduled to review the proposed Interior Finishes and Furniture Plans.

Hyman Hall Renovation: Preliminary floor layout plans have been presented & reviewed by the project end-user groups. Feedback and comments were noted and a follow up Final Program Presentation has been scheduled December 14.

Newark Security Upgrade: Plans for the project are at the 80% construction document phase.  Modifications are being made to adjust the project scope and budget.

 