Construction Update for the Week of October 2nd, 2017

    • Significant progress continues to be made with the Academic Core project. Work continues with all 3 buildings to include interior wall framing, Mechanical, Electrical & Plumbing preparations and fire proofing. Exterior Scaffolding is being installed in Building 1. Structural preparation work is in progress in the large tiered classroom in building 1.
    • Geothermal Ground Loop – Phase I project is now substantially completed. All work in Parking Lots A, D, E & K are now completed and these lots are currently open to staff and students
    • Building 5 Renovation & Hyman Hall Renovation: Both projects are underway with architects. Development of schematic design plans, potential designs, project scopes, and budgets are in progress.
    • Newark Security Upgrade: Plans for the project are at the 50% construction document phase.

 